Construction progress
The recovery center is already taking shape.
Current photographs and documented work show the main building, completed sports field, residential cabins, interior works and a hostel under construction in Fedorivka, Rivne region.
≈ €612Kestimated value already built
40–50%reported overall readiness
€2Mcampaign goal to complete the center
01Completed or in active use
- Four residential houses
- Dining hall and conference room
- Electricity connection
- Water well and water supply
- Sports field
- Asphalt access road
02Work currently underway
- Hostel construction
- Interior finishing
- Additional residential cabins
- Site infrastructure and landscaping preparation
03Funding will help complete
- Treatment building with a pool
- Six additional residential houses
- Medical and rehabilitation equipment
- Chapel, gazebos and landscaping
- Sports and children’s infrastructure
- Annual recovery programs
Help turn construction progress into lasting recovery.
Partners may support a specific building, equipment package or recovery program.
Support the center→